Who approves a subdivision in WA?
The Western Australian Planning Commission (WAPC) decides subdivision applications, not the local council. It refers each application to the local government and relevant agencies, such as servicing authorities, for comment before making its decision.
How long does the WAPC take to decide?
The WAPC generally has 90 days to decide a subdivision application, and the local government and referral agencies have 42 days to comment. A well-prepared application that answers the likely questions up front helps keep the process on time.
What happens after conditional approval?
Approval usually comes with conditions, such as servicing, road works or other requirements set by the local government and agencies. Each condition needs to be cleared by the relevant authority before the WAPC endorses the deposited plan and new titles can be created. We manage condition clearance through to titles.
How long is a subdivision approval valid, and can it be extended?
Three years for five lots or fewer, and four years for six lots or more. The WAPC can grant one extension of two years to the period for submitting the deposited plan, on Form 4A under section 145A of the Planning and Development Act 2005. You need to show you did everything reasonably practicable to meet the original period, and include local government correspondence confirming the plan is still consistent with the local planning framework. An application lodged with more than 6 months left on a 3-year approval, or more than 12 months left on a 4-year approval, may be viewed unfavourably.
Can I challenge a condition I can't meet?
Yes. You can ask the WAPC to reconsider within 28 days of the decision, or apply to the State Administrative Tribunal for review within 28 days. We can advise which route suits the situation.
Can heritage or environmental issues affect a subdivision?
Yes. Native vegetation, threatened species habitat such as black cockatoo habitat, Aboriginal heritage and heritage-listed places can all lead to conditions or redesign. Our heritage and ecology teams check these constraints in-house, so they are picked up before the application is lodged.
Do I need a surveyor as well as a planner?
Yes. A licensed surveyor prepares the plan of subdivision and the final deposited plan. A planner looks after the planning case, the referral process and the conditions. We work with your surveyor throughout.
What fees are involved?
WAPC application and endorsement fees are set by regulation and published in the WAPC's subdivision fee guide. Service agencies and local governments also charge for clearances and infrastructure. We'll outline the fees that apply to your site in our proposal.
Do the October 2026 draft R‑Codes change anything yet?
On 24 October 2026 the State Government released draft R‑Codes for consultation. Comment closes on 26 February 2027, and the current R‑Codes apply until changes are adopted. For blocks of 700 to 900 square metres, read our guide to
the R‑Codes reform and the 700sqm rule.